2009 Larimer County Chip Seal Schedule

 

Text Box: Areas Highlighted in yellow are complete
All chipseal and fog seal has been completed.  The roads that have not been highlighted will be restriped this week -  then they will be complete.

Construction Notes

·         Work may occur anytime Monday through Friday including night time hours for fog seal

·         Street cleaning may begin the prior the scheduled start date

·         Work may continue several days after the scheduled start date

·         Work schedule is dependent on the weather – subject to change

·         Expect 15 to 20 minute delays

·         Slow down to prevent broken windshields

What is Chip Seal

 

Send Email to Project Manager

 

Chip Seal Hot Line 970.498.5666

 

Chip Seal Area Maps

 

 

 

Number on Map

Location

Planned Start Date

 

1

CR 16 from CR3E east to County Line (WCR 13)

Monday

6/22/2009

 

2

CR 5 from CR14 north to I-25 Frontage Rd

Monday

6/22/2009

 

3

CR 16 from west Frontage road west to end of pavement

Tuesday

6/23/2009

 

4

CR 13C from CR 13 to SH 402

Tuesday

6/23/2009

 

5

Sierra Vista Terraces

Wednesday

6/24/2009

 

6

Cloverdale Acres (35th Street west of CR 15)

Wednesday

6/24/2009

 

7

Spring Mountain Ranch (Spring Mtn. Dr. & Spring Mtn. Ct.)

Thursday

6/25/2009

 

8

Manzanita Estates (Manzanita Dr. and Manzanita Ct.)

Thursday

6/25/2009

 

9

Bo-Mar (35th Street and 36th Street)

Monday

6/29/2009

 

10

Longs Peak Estates (Joni, Lisa, & Candy)

Monday

6/29/2009

 

11

Maplewood Estates (Rosewood Dr.)

Monday

6/29/2009

 

12

Colony Ridge

Tuesday

7/14/2009

 

13

Midway Acres (49th SW and Iowa Ave.)

Tuesday

7/1/2009

 

14

CR 10 from old US 287 east to County Line road

Wednesday

7/2/2009

 

17

CR 16E from CR21 west to Lon Hagler Reservoir

Monday

7/6/2009

 

18

CR 16 from CR21 east to End of Pavement

Monday

7/6/2009

 

19

CR 21 from CR 14 south to Lonetree Park (Lonetree Dr.)

Monday

7/6/2009

 

20

CR19 apron south of CR 16H

Monday

7/6/2009

 

21

Bonnell Acres (Bonnell Dr., Ruth, Morrey, Herb, & Esther Cts.)

Thursday

7/16/2009

 

15, 16, 22

Removed because of other scheduled work

 

23

CR 14 from east of CR23 to CR21

Wednesday

7/13/2009

 

24

CR 29 from CR 12 north to CR 18E

Wednesday

7/16/2009

 

25

CR 12 from CR 23 west to CR 29

Thursday

7/16/2009

 

26

CR 23 from CR 8E north to CR 14

Thur-Mon

7/16/2009

 

27

CR 8 from CR 21 west to CR 23

Monday

8/4/2009

 

28

CR 21 from CR 6 north to CR 8

Monday

7/22/2009

 

29

Vaquero Estates (Sundown, Evita, Ramona, Joyce, Tia, Candice Lucia)

Tuesday

7/20/2009

 

30

Wester Mini-Ranches (Sundown, Branding Iron, Chishom)

Wednesday

7/20/2009

 

31

CR 17 from CR 6E (Spartan Lane) north to old US-287

Thursday

7/21/2009

 

32

CR 31 from just south of North Shore Road south to CR8E

Monday

7/27/2009

 

33

CR 8E from CR 23 west to Hudson Pl.

Tuesday

8/3/2009

 

34

CR 8E from Hudson Pl.  West to CR27E

Wednesday

8/3/2009

 

35

CR 23 from CR 23E/6 east and north to CR 8

Wednesday

8/3/2009

Larimer County Seal Coat Schedule - 2009

 

The Larimer County Road and Bridge Department begins their 2009 Seal Coat Program on or about August 4th.  The 2009 Seal Coat area includes the southern Loveland and Berthoud areas.  Larimer County Road 20C is the northern boundary, and Larimer County Road 6 is the southern boundary.  Informational signs will be posted on affected roads detailing exact locations and time frames.  Our seal coat program differs from the chip seal program in that a very light coat of sand is applied after the sealing coat and no rocks are applied to the road surface.   Please call our Seal Coat project line at 498-5666 or visit our web page for schedule updates.

Traffic will be limited to one lane in these areas, expect delays of 10-15 minutes.  Motorists, bike riders and pedestrians may wish to choose alternate routes until the work is completed, usually no later than 48 hours after product application.  We encourage all traffic to drive slowly through the work zones and obey the posted speed limit to prevent materials that are being applied to the road from getting on vehicles.

Roads are listed in the order in which the work is expected to be completed. Informational signs will be posted on affected roads detailing exact locations and time frames. 

 

Road or Subdivision

Area to be sealed

 

Bonnell West PUD

Wild Plum Dr., Pronghorn Ct., Blue Mtn.

 

Mountain View Acres

Erving Ct., Bothun Rd., Lela Ct., Middle Rd.

 

LCR 14

From LCR 17 east to US-287

 

LCR 15H

From LCR14 south to Rosewood Dr.

 

LCR 13

From SH 60 north to LCR 16E

 

LCR 14

From LCR 23 east to LCR 17

 

LCR 10

From LCR 23 east to LCR 21

 

LCR 16

From McKenzie Dr. west to end of pavement

 

LCR 16

From LCR 21 west to LCR 23

 

LCR 16

From LCR 15 west for 1/2 mile

 

LCR 17

From 36th St. SW to Heart Wood Dr.

 

LCR 20E

From I-25 west to LCR 9

 

LCR 21

From LCR 14 north to LCR 18

 

LCR 21

From LCR 8 north to LCR 10

 

LCR 23 & LCR 16

From LCR 14 north and east to LCR 21

 

LCR 31

From North Shore Rd.  north to LCR 18E

 

LCR 31

From LCR 8E south to end of pavement

 

LCR 7

From SH 60 north to SH 402

 

LCR 8

From US-287 west to LCR 21

 

LCR 8E

From LCR 27E west to LCR 31

 

LCR 9

From LCR 16 north to SH 402